I. Council Action Requested.
Title
To award a contract for the Public Safety Building - Central Fire Station expansion and Police Station renovation to Great Falls Construction of Gorham, Maine in the amount of $4,300,000, said amount to be paid from the proceeds of general obligation bonds to be issued and estimated revenue surplus, and to authorize the town manager to execute a contract with Great Falls Construction and to take any other necessary action related thereto. This pricing for the project is a guaranteed not to exceed price within the RFP parameters.
Body
II. Basis for Council Action.
Council approval of this item is required because;
a. The Council has the authority to enter into contracts as the legislative body of the Town pursuant to Article II, Section 3(I) of the Charter, and
b. Article 22 of the approved town warrant of June 13, 2020 authorized "the Town to fund the appropriation by approving the terms and conditions of one or more agreements to effectuate the issuance of general obligation bonds (an notes in anticipation thereof) of the Town in a sum not to exceed $4,960,554, and
c. $3,600,000 of said amount is allotted "for the design, construction, improvement, expansion, repair and equipping of the police and fire station located at 375 Gray Road in the Town and related development of the site.
III. Issue Summary.
At its meeting of December 11, 2020, the Building Committee reviewed the proposals received along with recommendations of Harriman Architecture, lead on the town's design team for the project, for the award of the construction contract.
Seven proposals for construction were received with the following base bids:
Company
Base Bid
Grand Total
Benchmark
$ 4,247,173
$ 4,944,007
Blane Casey
$ 5,104,130
$ 5,631,814
Doten's Construction
$ 4,378,504
$ 4,813,704
Great Falls Construction
$ 3,803,745
$ 4,271,310
Hardypond Construction
$ 4,549,451
$ 4,885,858
Structuretone
$ 4,528,564
$ 5...