I. Council Action Requested.
Title
To authorize pre-approval design work for the joint maintenance facility project as outlined in a proposal from Allied Engineering dated July 10, 2017 in the amount of $153,215 to be funded through a combination of capital building improvements funds carried over from prior fiscal years and general contingency.
Body
II. Basis for Council Action.
Council approval of this item is required because;
a. the work would be funded partly through the use of capital building improvement funds, which would require re-prioritizing and re-programming some of those funds from other projects, requiring Council approval, and
b. the work would be funded partly through the use of general contingency funds, customarily approved by the Council.
III. Issue Summary.
Please see the attached fee proposal.